*

Crime Reduction Toolkits

Partnership Working

Crime - Let's bring it down
 
* *
*
* *

 
*
*
Toolkits Homepage
*
Toolkits Content
*
*
Introduction
*
What do we know
*
Local Solutions
*
Tackling The Problem
*
Making It Happen
*
Resources
*
Innovation
*
Practical Tools
*
Contact Points
*
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
*
*

Toolkit Index

Devise a Plan and Schedule

The core audit team should examine past Crime and Disorder Audits produced for your area. It will also be helpful to Consult those involved in producing the first audit on the tasks that they undertook – problems, constraints, advice, lessons learned etc - any subsequent interim audits.

The team should look to plan the sequence in which tasks need implementing, which elements can take place at the same time and which depend on other aspects of work being completed. For instance, initial data analysis could begin before the completion of all data collection.

Decide which members of the team will undertake specific tasks and which elements will be contracted out. Determine individuals’ availability and the proportion of time each week they could spend on the audit. If elements of the audit are contracted out, the whole contracting process will have to be planned in detail before actual work can begin.

An overall plan of the audit process with time-scales and elements of the work allocated to different individuals should now be drawn up. This information can be presented in a variety of ways (according to need and IT availability). Partnerships will most likely choose one or more of the following options:

  • Milestone Plan – this provides a range of key activities in the audit process and indicates the dates by which they need to be completed. The tasks identified in a Critical Path Analysis (see below) as having the potential to delay the whole process should be highlighted as being the most important to complete on time.
  • Responsibility Chart – this lists all of the tasks involved in the audit and the people with responsibility for ensuring their completion by set dates.

 

  • Critical Path Analysis – this can be produced by hand or MS Project by entering tasks and sub-tasks, their duration and deadlines. It will indicate which tasks, if not completed on time, will delay the entire project and which elements of the work can slip without a knock-on effect.
  • Gantt Chart – this shows each activity (e.g. data analysis, publication of audit) as a horizontal bar plotted on a timeline. It shows when and for how long each activity will occur and which elements of work will happen at the same time. Gantt is available on MS Project
  • Activity Network (or PERT chart) – this diagram shows how the different aspects of work on the audit are related to and reliant on each other. Links between the different elements of work show which tasks need to be completed before a specific aspect of the audit can begin. PERT is available in MS Project.

The Team should copy project plans or schedules produced in the initial planning of the audit to partner agencies for information, highlighting which sections, requirements or requests are directly applicable to specific organisations. This will ensure that not only core team members are fully aware of the range of tasks and tiimescales but that partners agencies are alerted to the workload and deadlines for submitting data. This will also set the scenario for the knock-on effect of potential slippage.

The audit timetable/plan should be a standing agenda item on partnership meetings (e.g. the board) to inform members of progress and of any difficulties which maybe arising. This will ensure that the Audit is regarded as a priority.

Back to Organisational Issues

<<Contents

 > Previous Section

> Next Section

 

*
   
** Back to Top    Site Help    Search    Contact Us    Site Map    Knowledgebase